Project Update


Screen Shot 2019-10-07 at 2.59.50 PM.png

Tower Building

The Tower Building wrap continues


Screen Shot 2019-10-07 at 3.00.00 PM.png

Masonry Work

The Masonry work is coming along very nicely!


Screen Shot 2019-10-07 at 3.00.10 PM.png

Stocking the building

Using lots of equipment to stock & unload from the building


Screen Shot 2019-10-07 at 3.00.18 PM.png

DDA Tour

The DDA touring the project


Screen Shot 2019-10-07 at 3.00.27 PM.png

Bathroom Tile

The tile in the restrooms is going on and look great


Screen Shot 2019-10-07 at 3.00.36 PM.png

Waterproofing

The courtyard waterproofing going down


Screen Shot 2019-10-07 at 3.00.43 PM.png

Connexion!

This is our microfiber duct rolls for City of Fort Collins Connexion Broadband


Screen Shot 2019-10-07 at 3.00.51 PM.png

WE HAVE POWER!

The building is now hooked up with City of Fort Collins Light & Power and energized


Upcoming Month

• Finish Rough Ins of Mechanical Systems in Plaza

• Finish Drywall in tower

• Begin Drywall in Plaza

• Break ground on Willow Plaza improvements

• Continue Siding & Exterior Skins

Past Month

• Dry in Plaza Building

• Begin Drywall in Tower

• Begin Rough in of Mechanical systems in Plaza Building

• Continue work on Willow/Linden Plaza

• Begin siding & exterior skins